Project Details

Full-Service Program Expansion:
18 Locations
Manufacture & Ship Only:
4 Additional Projects
Surveys & Permitting:
11 Locations
Survey & Installation Reporting:
24-Hour Documentation
Industry:
Healthcare
Client:
Chewy Vet Care
Sign Type:
Channel Letters, Commercial Graphics, Wall Signs
Region:
Nationwide
Program Type:
Multi-Location Signage Program

Chewy Multi-Location Signage Rollout

Thomas Sign supported Chewy’s expansion with a multi-location signage program covering site surveys, permitting, engineering, manufacturing, installation, and project management for interior and exterior signage.

Chewy Vet Care waiting area with custom interior wall graphics, pet scale branding, and animal artwork.

Regional Rollout of Interior & Exterior Signage

The Challenge

Chewy partnered with Thomas Sign to support its regional expansion through a multi-location signage program. The project required coordination across multiple sites, each with different permitting requirements, landlord restrictions, site conditions, and construction schedules.

Thomas Sign was responsible for site surveys, permitting, manufacturing and installation of interior and exterior signage, vendor coordination, approvals, and field management.

Our Solution

Thomas Sign worked directly with Chewy’s creative team and general contractors to maintain consistent brand standards across locations while accommodating individual site conditions.

Our team completed site surveys and permitting at 11 locations and coordinated municipal and landlord requirements. Survey and installation documentation was uploaded to the TSA Portal within 24 hours. Our engineering team also developed mounting and manufacturing solutions based on the architectural requirements of each location.

The Results

The program began as a four-site pilot and expanded to 18 full-service locations, along with four additional manufacture-and-ship-only projects.

Most installations were completed within one to two weeks of their original target dates despite construction-related delays. All work was completed before site turnover while remaining within the established budget and scope.